http://www.rcaanews.org/rcaa

Aircraft Noise Group* Response on Noise to the Expert Panel

*Now the Seattle RCAA


	Aircraft Noise Group Response


     __________________________________
     In the Matter of:
     Expert Arbitration Panel's Review  of
     Noise and Demand/System
     Management Issues at Sea-Tac
     International Airport
    __________________________________


             RESPONSE TO PROCEDURAL ORDER OF EXPERT
                        ARBITRATION PANEL

Organization of responses and enclosures

PART 1:   We have organized our responses into two parts: Part 1
covers the first question listed in the Panel's scope in Page 4
of the Order.  Responses to questions 2 and 3 of the order are
incorporated into Sections 2 & 3 of our Part 2.
	"Question 1. Has the Panel been asked to determine
	whether the goals of the Noise Budget and the
	Nighttime Limitations  Program, if achieved, would produce a
	significant reduction in real noise impacts on-the-ground?

 	Question 2.  If so, would achievement of the noise reduction
     	performance objectives of the Noise Budget and Nighttime
         	Limitations Program produce a significant reduction in
     	real noise impacts on-the-ground?

 	Question 3.  Is the Noise Validation Methodology proposed
	in by the POS a reliable method for determining, on the basis
         	of measurements of actual on-the-ground noise using the
     	existing noise monitoring system at Sea-Tac, whether
         	the noise reduction performance objectives of the Noise
    	 Budget and Nighttime Limitations Program have been
    	 achieved?"

PART 2:   Part 2 of our comments covers the information the Panel
requested the public to submit on page 8 of the Procedural Order
in addition to responses to questions 2& 3 above.
	"Request 1.       Summaries of any methodologically sound
  	aviation noise data collected by local community
 	organizations or individuals.  These summaries must be
	documented with specific information on the procedures (including
   	calibration),  time of day, date, locations, and equipment used to
   	collect the data, as well as a brief description of airport operations
            during the measurements (e.g. north or south flow, nature of noise
	[flyovers, ground run-up, etc.], background sources
            and levels, and weather conditions.)

	Request  2     Detailed descriptions of any technical reasons
   	why achievement of the noise reduction performance objectives
   	of the Noise Budget and Nighttime Limitations Program
   	established by the POS would not be expected to produce a
   	significant reduction in real noise impacts on-the-ground.

	Request 3.  Detailed descriptions of any technical reasons
   	why the Noise Validation Method proposed by the POS should
   	not be found to be a reliable method for determining, on
   	the basis of measurement of actual on-the-ground noise using
  	the existing monitoring system at Sea-Tac, whether the
   	noise reduction performance objective of the Noise Budget and
            Nighttime Limitations Program have been achieved.

APPENDIX
     To assist the panel, we have attached an Appendix containing
either full copies or the appropriate portions of copies of any
documents or reports referred to in our responses.  If copies
were unavailable to us, we have provided a complete citation.  If
the copies are already available to the Panel, such as PSRC
minutes, we make a note but don't include the copies.


Part 1:
     The Expert Panel must determine whether the goals of the
Noise Budget and Nighttime Limitations Program would produce a
significant reduction in real noise impacts on-the-ground.  This
program was adopted by Port for a different purpose at an earlier
time.  It has offered it here as serving a new purpose, that of
PSRC Res. 93-03 and third runway expansion as well.  The public
disagreed that it could serve two conflicting purposes.  The PSRC
decided to accept the Noise Budget and Nighttime Limitations
program on the condition that it could be established by and
independent panel that it did suit the new purpose and would
produce a significant reduction in real noise on-the-ground.  The
independent expert panel is supposed to settle this issue and
cannot do so without deciding whether the or not the goals of the
program would in fact produce a significant reduction in real
noise impacts on the ground.

     An independent panel was chosen to arbitrate the issue
because the Port of Seattle sits rambunctiously on the PSRC
itself, thereby serving as both an vigorous advocate of its own
proposals and self-interest and as a decision-maker on those very
same proposals, precluding the PSRC from fairly deciding these
issues itself.  If the Expert Panel failed to determine whether
the entire Noise Budget & Nighttime Limitations program--
including its goals--would produce significant reductions, it
would be failing to do the very task it was assigned.

     The Noise Budget and Nighttime Limitations program was
adopted as the result of the "Noise Mediation" process.  However,
the goals it is important to know that the goals were not adopted
as part of the mediation process.  The Mediation was unilaterally
terminated by the Port, and the citizen caucuses dismissed prior
to the choice of goals.  These goals were chosen by Port staff
after the termination and were announced six months later.

     In fact, there was no mediation agreement adopting the Noise
Budget and Nighttime Limitations program.  Attached is a Sea-Tac
Noise Bulletin from our group which was widely distributed both
in the neighborhoods and to local public officials at the time of
the Port unilaterally terminated mediation.   A portion of the
"agreement" presented at that last mediation session is
reproduced showing that the goals were not filled in on the
proposed draft agreement passed out on the day mediation was
terminated.  No agreement was ever signed, nor did the mediators
representing the Citizens causes have authority to sign them.

     This newsletter also makes clear that the Mediation that
produced the Noise Budget occurred prior to institution of the 4-
Post Flight rerouting.  In the subsequent lawsuit Seattle
Community Council Federation vs. F.A.A. that followed, the F.A.A.
argued that one of the reasons that there would be no significant
impacts from 4-post because no third runway was planned.  The
Noise Budget and Nighttime Limitations Program did not
contemplate a third runway adding an estimated additional 100,000
operations per year.  This is why the reductions of noise impact
on the ground must be "significant."

     The term "on-the-ground" refers to three issues.  First the
reduction of engine noise via the certification process does not
necessarily translate into actual noise reduction because the
weight of the aircraft and pilot procedures significantly affect
the amount of real noise generated on the ground.  Second, local
terrain also significantly affects how much noise is received on
the ground.  Third, the number and demographic characteristics of
people living on the ground beneath the roar affects the
significance of the impacts.  The F.A.A. estimates that 66,000
people currently reside in 65+DNL.  In the Flightplan DEIS, the
Port argued that there would be significant noise reduction
because only 2000 would be left in 2010 the rest having been
driven out by the noise in the intervening years.  (The Port has
no plans to buy them all out, only a very few.)  Deciding if this
sort of environmental "cleansing policy" constitutes a reduction
in real noise impacts on the ground also comes under the purview
of the Expert Panel.

     Finally, the noise portion of the resolution was passed in
part because of complaints from the public in comments on the
(PSRC) Flightplan DEIS1 that the goals of the Noise Budget and
Nighttime Limitations Program would not produce reduced real
noise impacts and that the methodology for measuring them was
both theoretical, (not "real"), exempted international and
military over flights, did not include run-ups, did not
significantly reduce real impacts on real people, and was
technically inadequate.

     In light of this, the public certainly believed that the
resolution proposed to settle these controversies cure these
problems by requiring independent review of both the goals and
the methodology.

     The legislative history of the resolution supports this
interpretation, as well.  The Port through its position on the
PSRC offered proposals to change the resolution to preclude
review of the goals and to rubber-stamp the methodology, but
these proposals were rejected by the PSRC in favor of the present
language.  We review the legislative history below.


Legislative history
     Because the Panel has not been asked consistently in all
documents and in plain English to determine question #1, we need
to review what each document says and how the intent of the
Executive Board can be deciphered from these sources.  The
analysis below reviews each of the documents chronologically.

4-93 Paragraph #2c of PSRC Resolution A93-03 passed 4/93    2
     spelled out that the "noise reduction performance objectives
     are scheduled based on independent evaluation..."  The
     resolution further spells out that only the Executive Board
     is directed to:  1)  Take all necessary steps to "implement
     this resolution."  That means that the General Assembly
     delegated the issue of implementation to the Executive
     Board, but called for an "independent" evaluation of the
     "objectives," which can only refer to the Panel deciding if
     the "objectives" are sufficient.

8/93 Page 1-2 and 20-31 of a report by Apogee Research, Inc.
     dated 8/23/933 that was done for PSRC.  On page 29, it says
     that "this panel would provide advice on monitoring
     techniques and objectives and review findings..."  The
     report is referring to the Expert Arbitration Panel.

9/20/93   A  memo to the Executive Committee from Mary McCumber
     dated 9/20/934 was faxed to the committee  members before
     the 9/23/93 meeting and contains both the PSRC staff and the
     Port proposals for key paragraphs III.C, III.F and paragraph
     5.b of Appendix A in the final version of the Implementation
     resolution.  The handwriting on the memo shows where the
     words "reasonable, meaningful" were stricken from III.C,
     III.F and 5.b as well as how the words "validate the
     methodology to determine" was substituted for "to decide" in
     5.b.  More importantly, it shows the Port's proposals
     rejected by the Executive Board (see 9/23/93 minutes below.)
     The differences between the Port & staff language is key to
     understanding the intent of the Executive Board's decision.
          The Port proposal for III.C tried unsuccessfully to 1)
     eliminate the word "independent";  2) to replace "that" with
     "to establish that";  3) to replace "are sufficient to cause
     a reduction" with "result in a reduction" and  4) replace
     "reduction in measurable real ("on the ground") noise" with
     "reduction in on-the-ground noise."  The last sentence in
     the Port's proposal would have practically guaranteed the
     Port that the data from the Port's monitoring system would
     have been conclusive proof that there had been "on-the-
     ground noise reduction."  The PSRC staff proposal, however,
     leaves to the Panel the decision of how to utilize data from
     the "existing airport noise monitoring system" to determine
     if there is a "significant reduction in real noise impacts
     on-the-ground."  This should include a Panel determination
     of what constitutes a significant noise reduction to a
     human, not only an instrument.
          The Port's losing proposal for paragraph 5.b tried to
     eliminate the entire sufficiency issue by not having the
     Panel meet until 1996 and by eliminating the words
     "sufficient to cause a reduction..."  The other differences
     in this paragraph are in line with the ones described above.
          As can be seen from the discussion below of the final
     version of the Implementation resolution, any of the Port's
     language in paragraph III.C would have basically rubber-
     stamped any goals and methodology that the Port would
     develop.  It is important to remember that the Port fought
     to have its meaningless methodology rubber-stamped over a
     year ago, and lost.  That the Port is now trying to fight
     the same battle all over again with the Panel shows
     incredible arrogance and bad faith.  Our citizens take it as
     evidence that the Port itself doesn't believe that the goals
     and methodology of the Noise Budget & Nighttime Limitations
     Program can meet the tests of independent review showing
     "real reductions of noise impacts on the ground."
          The fact that Jerry Dinndorf is now siding with the
     Port's opinion about this matter after PSRC stood up for
     their own language one year ago can only be explained by
     internal politics within PSRC.  We will not bore the Panel
     with these politics, but only reference PSRC attorney David
     Bricklin's statement in the 9/23/94 minutes that paragraph
     III.C is "where we have a difference of opinion with the
     Port."  The differences in the two versions can stand for
     themselves and prove clearly that the intent of the
     Implementation resolution is according to our
     interpretation.

9/23/93   Final version of the A93-03 Implementation Resolution:
     Part III.A of the Implementation resolution shows that the
     language does not define any limits on what constitutes
     "noise reduction objectives."  The language here merely
     states that 3 programs are "responsive" to the call of A93-
     03, which indicates that other programs could also be
     "responsive" to A93-03 at the discretion of the Panel.
     Paragraph III.C says a "method of independent validation
     needs to be developed that [sic] the Noise Budget and
     Nighttime Limitation Program noise reduction objectives are
     sufficient to cause a reduction in measurable real ("on the
     ground") noise by 1996."  (emphasis ours)

          This sentence talks clearly about a method to validate
     the objectives NOT to actually do the validation nor to
     decide the objectives.  The word "validate" means "to prove
     to be valid; confirm the validity of" according to Webster,
     clearly confirming our interpretation here.  If the Port's
     consultant, Mestre Greve, performs the validation, it is not
     independent.  Validating the sufficiency of the noise
     reduction objectives is clearly the job of the Expert Panel.
          Moreover, the term "independent validation" does not
     bind the Panel to a delimited definition of what does or
     does not constitute and independent evaluation.  Neither
     does it bind the Panel to what does or does not fall within
     the definition of noise reduction objectives.
          Finally, the word "that" in the Paragraph III C.
     sentence should be replaced by the word "whether" because
     that is the obvious usage.  Appendix A, #5.b supports this
     as well because it contains exactly the same sentence,
     except that the ungrammatical "that" has already been
     replaced with "whether."  Otherwise, the sentence would
     imply that an "independent" Panel would "validate" (rubber-
     stamp) the Noise Budget & Nighttime Noise Limitations,
     clearly not intended.  Mr. Dinndorf reinforces this
     interpretation by referring to the Appendix A language in
     his 8/11/94 letter with "Requirements for the Expert
     Arbitration Panel."

     Paragraph III D decides that the Coordinating committee will
     decide what issues should be addressed by the Panel when the
     independent Panel validates the methodology for noise
     reduction.  Thus, paragraph III.D does NOT say that the
     Coordinating Committee should decide the objectives, but
     only that it agree on a "validation methodology," which they
     did per Appendix B.  The minimum issues to be addressed in
     this "method to validate" are contained in Appendix B to the
     Memorandum of Agreement as explained below.  In other words,
     the Panel is free to add other issues.

     Paragraph III.F supports the above conclusions.

     Paragraph 5.b decided that the Panel should meet in 1994
     instead of 1996, as suggested by the Port, for the reasons
     already mentioned in the 9/23/93 minutes, namely that the
     Panel should have "...up front, an expert role in
     establishing what those reductions are..."  In addition, the
     language, including the word "sufficient" in this paragraph
     clearly expresses the desire of the Executive Board to have
     the panel answer question #2 on Page 4 of the Panel's
     9/22/94 Procedural Order.

3/94 In the Memorandum of Understanding (MOU), Paragraphs II.D,
     II.E and Appendix B are the key parts.  These paragraphs
     only concern themselves with "The method to validate" and
     not with deciding the "objectives" themselves.  This is in
     total agreement with III.D of the 93-03 Implementation
     Resolution which includes the sufficiency issue.
          It is also important to realize that the MOU is not
     adopted by the Executive Board but by the Coordinating
     committee, so nothing in the MOU will change the intent of
     the Executive Board.  The Executive Board only delegated the
     "development of the validation Methodology" to the
     Coordinating Committee through III.D, but not the setting of
     the objectives.

     In Paragraph II.D the word "ensure" says only that the
     Coordinating Committee wants to make sure that the Panel
     addresses all of the issues in Appendix B.  In Appendix B to
     the MOU, the Coordinating Committee calls for some minimum
     issues to be addressed in this "method to validate."  In
     other words, the Panel is free to add other issues.

     Paragraph III.D  says that the Coordinating Committee will
     decide what issues should be addressed by the Panel when the
     independent Panel validates the methodology for noise
     reduction.  The minimum issues to be addressed in this
     "method to validate" are contained in Appendix B to the MOU
     as explained below.  In other words, the Panel is free to
     add other issues.

8/94 The 8/14/94 letter from Mr. Jerry Dinndorf again confirms
     the interpretation by enclosing Appendix A of the A93-03
     Implementation resolution (see 9/93) above) under the
     enclosure labeled "Requirements of the Expert Arbitration
     Panel and Schedule."

8/94 The 8/19/94 letter from Mr. Jerry Dinndorf does not change
     the above facts for the following reasons:

          1. The letter is only signed by Mr. Dinndorf.  There
             are no signatures by the other three members of the
             Coordinating committee, nor any minutes of any
             meeting where the conclusions of the letter are
             supported by the other members of the Coordinating
             Committee.
          2. The Coordinating Committee cannot adopt the Noise
             Budget and the Nighttime Limitations Program as the
             objective referred to in III.C of the
             Implementation Resolution retroactively.
             Therefore, this letter should not be viewed as n
             adoption of these objectives by the Coordinating
             Committee, but as an interpretation by Jerry
             Dinndorf personally as the Chair.
          3. Mr. Dinndorf's assertion on Page 3 that "since
             [sic] the Executive Board has adopted these
             programs as the objectives to be achieve, it is not
             within the scope of the Panel to consider their
             adequacy..."  should be assessed against the actual
             documents above.  The above documents show that Mr.
             Dinndorf's statement is not true.  On the contrary,
             the Executive specifically rejected the Port's
             version of paragraph III.C in the Implementation
             resolution at their 9/23/93 meeting.  The Port's
             proposal tried to insert language into III.C that
             more closely resembled Mr. Dinndorf's
             interpretation.
                  The only document that has come even close to
             an adoption of the two programs as the "objective"
             is the MOU, Paragraphs II.D and Appendix B.
             However, both only concern themselves with "The
             Method to validate" and not with the "objectives"
             themselves.  This is in complete agreement with
             III.D of the Implementation resolution that calls
             for the Coordinating Committee to deal with the
             "validation methodology" only.  Finally, the MOU is
             not adopted by the Executive Board but by the
             Coordination Committee.

          4. Mr. Dinndorf is actually saying that the Panel has
             been authorized to answer question #2 on page 4 of
             the 9/22/94 Order.  In the last 2 paragraphs on
             page 3, Mr. Dinndorf says that "the charge to the
             Panel is to assess the appropriateness of the
             methodology. [emphasis ours]" which is the same as
             question #2 on Page 4 of the Order, even though Mr.
             Dinndorf labels these two paragraphs as the "third
             question."
                  Mr. Dinndorf also says in Par., pg. 3 of his
             letter that "since [sic] the Executive Board has
             adopted these programs as the objectives to be
             achieved, it is not within the scope of the Panel
             to consider their adequacy..."  This is completely
             contradicted by the sentence in paragraph 5.b of
             Appendix A of A93-03 in the Implementation
             Resolution.  It says very specifically that the
             Panel shall determine "whether the Noise Budget and
             Nighttime Limitations program are sufficient to
             cause the only thing that the Executive Board
             adopted was to have the Panel decide whether these
             two programs are sufficient."

          5. Mr. Dinndorf has clearly changed his mind about
             this subject as can be seen from his own
             instruction letter to the panel on 8/11/94.  When
             he was asked by the panel about this the first time
             at the Panel hearings on 8/12/94, he interpreted
             A93-03 the same way as we have done above.  Later
             on the same day, after a break in the proceedings,
             he modified this to resemble his states in
             paragraph 3 above!  This is a clear case of
             somebody wanting to change the rules of the game
             when things are not going his way.

          6. Our assertion is that Mr. Dinndorf (and possibly
             the entire Coordinating Committee) has not only
             changed his position about this issue, but is a
             belated effort to change the language and meaning
             of the resolutions passed by the Executive Board in
             a way that would narrow promised independence of
             the Panel to a rubber stamp for Port and prevent it
             from telling the Executive if in fact the Noise
             Budget and Nighttime Limitations program would
             produce a significant reduction in real noise
             impacts on the ground.

_______________________________
1  We have not enclosed the Flightplan DEIS & the citizens
comment documents in this instance because these comments are
sprinkled throughout a bound volume of 500 pages which cost the
public $35 to purchase.  Copies of both the FlightPlan DEIS & the
Comments are available from the PSRC and the POS should the Panel
wish to review them.
2  We assume the Panel has copies of Resolution A93-03
3  See Appendix
4  See Appendix