|
Document reformatted for the the world wide web
Rachael Paschal Osborn
attorney at law (Address omitted) February 15, 2001
U.S. Army Corps of Engineers Regulatory Branch PO Box 3755 Seattle, WA 98124 Attn: Jonathan Freedman,
Project Manager
Washington State Department of Ecology Shorelands & Environmental Assistance Program 3190 – 160th Ave. S.E. Bellevue, WA 98008-5452 Attn: Ann Kenny, Environmental
Specialist
Re: Port of Seattle, Ref. No. 1996-4-02325
Dear Mr. Freedman and Ms. Kenny,
This letter comprises comments regarding water resource elements
of the Port of Seattle’s application for a Section 401 certification
and Section 404 permit for the proposed Third Runway Project and associated
construction. These comments
are submitted on behalf of Airport Communities Coalition, composed of
the Cities of Burien, Des Moines, Federal Way, Normandy Park, Tukwila,
and the Highline School District. These
communities are vitally concerned with the health of the streams and
watersheds located within their communities. They object to any approval
by the Department of Ecology of the Port’s proposal that does not provide
verifiable, real assurance that local streams, water quality, and the
fish and wildlife dependent on them will be maintained and protected.
The analysis contained in this letter
is pertinent to your upcoming decision regarding the Port’s application
for a Section 401 certification. The Port admits that activities associated with the
Third Runway construction proposal will reduce late summer flows in
the three stream systems that surround Sea-Tac International Airport. Supplement to Biological Assessment, p. 2 (Parametrix
Dec. 2000). Impacted streams
are already degraded for flow-related water quality parameters such
as temperature and dissolved oxygen.
Sea-Tac Runway Fill Hydrologic Studies Report (Pacific Groundwater
Group, June 19, 2000). These
flow reductions and associated water quality impacts, if not addressed,
would be inconsistent with state certification and approval. These issues must be resolved before 401 certification may issue.
These comments focus in particular on the low streamflow mitigation
proposal submitted by the Port, and associated water right requirements.
In sum, the Port: (1) does not provide a credible analysis of
the impacts of its proposal on base flows in Miller, Walker and Des
Moines Creeks, (2) does not provide a certain method by which those
impacts will be mitigated, and (3) does not address legal requirements
under the state water code. Moreover,
the Port’s proposals for alleviating stormwater impacts and peak flow
damage will themselves contribute to low flow problems.
As a consequence, the Port’s proposal provides no basis for a
finding of reasonable assurance that water quality standards will be
met.
Set forth below
is information relating to the water quality and beneficial use problems
that must be mitigated by the Port, a review of the various options
for streamflow augmentation gleaned from recent Port submittals, a discussion
of the facts and issues associated with the water rights proposed for
use by the Port as a part of its water quality mitigation project, and
a brief review of relevant water quality law.
Section 401
of the Clean Water Act (33 U.S.C. § 1341) and its implementing regulation,
40 C.F.R. § 121.2(a)(3), require the Department of Ecology to certify,
with “reasonable assurance,” that the airport expansion, facilitated
by permits from both the Federal Aviation Administration and the Army
Corps of Engineers, will be conducted in a manner that does not violate
Washington’s water quality standards.
To achieve “reasonable assurance,” the Port of Seattle must develop
concrete and detailed plans and designs for its projects.
Speculative plans and concept-only designs do not provide the
level of assurance that state law requires to ensure that water quality
standards can be met.
Among the many
flaws associated with mitigation plans for the airport expansion, the
Port has failed to identify specific and credible sources of augmentation
water to meet its mitigation goals.
Consequently, these plans do not provide reasonable assurance
that the proposed mitigation activities will occur in a manner that
prevents violation of state water quality standards.
The “reasonable
assurance” standard requires a high level of certitude when water rights
are an element in the project design requiring certification. Many water rights in Washington are subject
to significant uncertainty concerning quantity and validity. The water rights documents found in the files
of the Department of Ecology’s Water Resources Program – permits, certificates
and claims – often bear little resemblance to actual, on-the-ground
water usage or the final administrative determination of validity that
the Department and the courts must make when transfers or changes are
proposed. Water rights can and
do change over time, depending on factors such as non-use, reasonable
efficiency and priority of use. As
a result, it is necessary that applicants provide valid rights prior
to certification when augmentation is a component of a water quality
plan.
The Port’s
proposals to augment streamflow in Des Moines, Walker and Miller Creeks
provide apt illustration of this problem.
The Port has yet to offer a valid water right or other credible
source of water in support of its plans to augment flow in Des Moines
Creek, notwithstanding specific water rights problems associated with
its two prior Section 401 applications.
In Miller Creek, the Port proposes a water right retirement strategy
that raises concerns about beneficial quantities.
A new augmentation strategy involving stormwater releases appears
to be an improper attempt to bypass water permitting requirements. In each case, the lack of certain water supply makes it impossible
to certify the viability of the plan. Each of these issues is discussed in detail below.
A.
Water Quality Requirements
Before discussing
the water right problems associated with the Port’s augmentation plans,
it is useful to review why the Port is proposing augmentation. The airport expansion project will, because
of the quantity of fill involved, obliterate wetlands and a significant
reach of Miller Creek and create large quantities of new impervious
surfaces. These changes will disrupt hydrologic recharge
and discharge functions for Miller, Walker and Des Moines Creeks, exacerbating
degradation of water quality and fisheries habitat. There are significant legal ramifications to
these problems.
(1) Washington’s Water Quality Standards
Water body
classifications for Des Moines, Walker and Miller Creeks are derived
from the general classification rule for water quality standards, WAC
173-201A-120(6). Because the
streams discharge into Puget Sound east of Hartstene Island, the Puget
Sound water quality standard governs.
That standard is Class AA, and applies to all three streams.
WAC 173-201A-140(21).
Class AA water
bodies are defined as “extraordinary” and must “markedly and uniformly
exceed the requirements for all or substantially all uses.” WAC 173-201A-030(1)(a). Characteristic use regulations require that
Miller, Walker and Des Moines Creek waters be clean enough to support
water supply, recreational use, and the migration, rearing, spawning
and harvesting of salmonid and other fishes.
WAC 173-201A-030(1)(c).
Water quality
criteria require that Miller, Walker and Des Moines Creeks meet specific
standards for dissolved oxygen, fecal coliform, temperature, pH, turbidity,
and toxic substances. WAC 173-201A-030(c).
The same standard also requires that the three streams be of
sufficient quality to not impair aesthetic values, i.e., offend senses
of sight, smell, touch or taste.
Finally, the
state anti-degradation rule requires that existing beneficial uses of
Miller, Walker and Des Moines Creeks be maintained and protected, and
that no additional degradation be allowed which would interfere with
or harm existing uses. WAC 173-201A-070.
Guidance for
applying Washington’s water quality standards in the context of a Section
401 certification is found in the two court decisions resolving the
City of Tacoma’s ill-fated Elkhorn hydroelectric project. Both the U.S. Supreme Court and the Washington Supreme Court approved
the imposition of conditions upon a Section 401 certificate requiring
the project proponent to maintain the characteristic uses of the affected
water body. Department of
Ecology v. PUD No. 1, 121 Wn.2d 179 (1993), affirmed, PUD
No. 1 of Jefferson County v. Washington Department of Ecology, 114
U.S. 1900 (1994).
In the Elkhorn
decisions, the courts upheld Ecology’s decision to require Tacoma to
maintain streamflow levels adequate to protect salmonid fisheries in
the Dosewallips River. Thus
it is Ecology’s duty, in reviewing the Port of Seattle’s Section 401
application, to prohibit degradation not only to the chemical and physical
quality of Miller, Walker and Des Moines Creeks, but also to protect
the capacity of the Creeks to support biological uses such as salmon
migration and spawning. Other characteristic uses, such as recreation,
as well as aesthetic standards, must also be maintained.
The project
may not be approved if the Port has failed to provide a permanent reliable
means to maintain flow in the late summer season. Thus, in reviewing the 401 application, you must look to the elements
of the Port’s proposed augmentation plan and its specific relationship
to state water quality requirements to determine whether the reasonable
assurance standard is met.
In reviewing
those plans, water is an essential component.
Yet, as detailed below, at this critical juncture in the Section
401 decision process, the Port does not have a credible water source
for its augmentation plans. Water
rights are uncertain with respect to Miller, Walker and Des Moines Creeks. Consequently, there is no way of knowing at
this time whether the Port will be able to provide the most basic ingredient
of augmentation. As a result,
reasonable assurance is not achieved, and the 401 certification must
be denied.
(2) Water Quality in Miller Creek, Walker Creek, and Des Moines Creek
Notwithstanding
state and federal water quality requirements, Des Moines, Walker and
Miller Creeks do not presently meet standards nor fully support all
legal beneficial uses. According
to the Low Streamflow Analysis, construction of the Third Runway project
will reduce flows in Miller, Walker and Des Moines Creeks during low
flow periods when water quality is already stressed.
Low Streamflow Analysis, Tables 9, 11, 12, 13.
Nor do these
three streams measure up to water quality standards. The Sea-Tac Runway Fill Hydrologic Studies Report (PGG, June 19,
2000) provides baseline information about water quality and fisheries
habitat. Des Moines and Miller Creek have routinely
violated water quality criteria over the years. PGG’s independent sampling revealed low dissolved oxygen in Walker
Creek. The Port’s Natural Resources
Mitigation Plan (December 2000) and the Des Moines Creek Basin Plan
(November 1997) also describe prior water quality studies and their
results, most particularly the history of violations of water quality
standards in Miller and Des Moines Creeks.
Des Moines Creek is also listed on the state’s 1998 303(d) list
for violation of the fecal coliform standard.
Miller and
Des Moines Creeks are both classified as Class II salmon-bearing waters
by the state Department of Fish & Wildlife.
Both support populations of salmonid fish, including native and
hatchery Coho salmon and sea-run cutthroat trout, as well as other resident
fish. Walker Creek contains an abundant supply of
cutthroat
trout in addition to juvenile Coho salmon.
These fisheries rely upon
cold, clean, flowing water for survival.
The PGG study indicated that low flow and water quality problems
contribute to fisheries habitat degradation.
The reductions in flow that would be
caused by the Port’s expansion projects are expected to exacerbate degradation
of water quality and fisheries habitat.
The Des Moines Creek Basin Plan (Nov. 1997) indicates that increased
impervious surfaces on the order of that proposed by the Sea-Tac expansion
will further reduce base flows and degrade water quality. The Port’s proposed expansion will, unmitigated, impede state and
local efforts to restore water quality to Des Moines, Walker and Miller
Creeks and will harm the biological integrity of these streams. See, e.g., previous comments and February
2001 comments (all in the 401/404 record in this matter) of Dr. Peter
Willing of Water Resources Consulting, Bill Rozeboom and Dr. Malcolm
Leytham of Northwest Hydraulic Consultants, Dr. John Strand of Columbia
Biological Assessments, and Dr. Tracy Hillman of BioAnalysts.
All three streams
also support local recreational use.
Large amounts of volunteer and city investment and restoration
money have been focused on restoring Des Moines Creek Park, which is
the subject of a vigorous community effort to protect the stream as
a resource treasure. A paved path adjacent to Des Moines Creek provides
a valuable recreational opportunity for use by local residents who walk,
jog and bicycle the Creek. The
streams also support trout fisheries.
Decreased flows and water quality will interfere with public
uses of the stream. Further,
there is little, if any, discussion of these beneficial uses in the
Port’s submittals.
In sum, Des
Moines, Walker and Miller Creeks are urban streams that continue to
support public use and aquatic life systems, uses that will suffer additional
degradation as a consequence of Sea-Tac expansion. These uses and their degradation are central to the Department’s
inquiry under the Section 401 process.
(3) Technical Deficiencies of the Augmentation Plan
The recent
Battle Mountain Gold decision provides additional insight into how the
reasonable assurance standard should be interpreted to apply to the
technical aspects of the Port’s mitigation plan.
Okanogan Highlands Alliance v. Ecology, PCHB No. 97-146,
et al., Final Findings of Fact, Conclusions of Law and Order (1/19/00).
Like the Port, Battle Mountain Gold (BMG) proposed water treatment
facilities and off-site wetland mitigation to offset the water quality
and aquatic resource impacts associated with its proposed gold mine. Unlike the Port, BMG’s mitigation plan was
detailed in concept and design. There
is barely a comparison to be made between the quality of the BMG plan
and what has been offered to date by the Port.
The PCHB
rejected BMG’s plans and reversed Ecology’s issuance of a 401 certification
due to flaws that are identical to those found in the Port’s plan. The Port’s proposed expansion project is predicted
to cause violations of water quality standards. At present, the sketchy augmentation plan identifies
the need for permanent treatment facilities and offers up concepts,
but provides little or no reliable information about design, construction,
operation and maintenance in perpetuity.
There is inadequate discussion of the relationship of the plan
to water quality violations and degradation in Des Moines, Walker and
Miller Creeks.
In sum, in
carrying out its duties under the Section 401 certification process,
the Department must consider the impact of the Port’s proposal on the
chemical, physical and biological characteristics of Miller, Walker
and Des Moines Creeks. It must
analyze the technical elements of the Port’s proposals to offset degradation
to these characteristics to ensure that each component of the plan can
be achieved, and in performing such analysis, it may not accept IOUs.
B. Low Flow Augmentation Options
The documents submitted by the Port discussing its streamflow
augmentation plans are confusing and inconsistent. The Port has yet to select a mechanism by which
it will mitigate the harm to late summer base flows in the Des Moines,
Walker and Miller Creek basins caused by the Third Runway Project and
associated construction. While
the Port has identified a range of options in its various submittals,
the documents are inconsistent and do not provide adequate technical
information to evaluate the implementation elements of mitigation and
their effectiveness. Some of the submittals seem to indicate that
augmentation will not work; the Port even acknowledges that the benefits
of one of its proposals cannot be measured.
The augmentation program discussed in the Comprehensive Stormwater
Management Plan (Parametrix, Dec. 2000, Agency Review draft) conflicts
with two other Port submittals addressing the same subject, the Supplement
to the Biological Assessment (Parametrix, Dec. 2000), and the Low Streamflow
Analysis (Earth Tech Inc., Dec. 2000).
These three documents, which presumably should provide a definitive
and integrated description of the Port’s streamflow augmentation plans,
in fact do not describe what plans the Port intends to implement in
order to augment low flow. Nor
do they describe what the actual streamflow benefits will be, or whether
state water law requirements are satisfied.
The Department of Ecology cannot make a finding that water quality
standards will be met with reasonable assurance based on the information
provided in these submittals.
(1)
Comprehensive
Stormwater Management Plan
The Comprehensive Stormwater Management Plan (CSMP) at pages
6-10 and 6-11 states that augmentation in Miller Creek will be accomplished
via retirement of existing water rights.
In the Des Moines Creek basin, according to the CSMP, a “Port-owned
well located within the Tyee Valley Golf course” will provide augmentation
water. Id.
Analysis of the Miller Creek proposal raises questions about
the augmentation benefits of this proposal.
Appendix G of the CSMP reveals that, upon investigation of actual
water use in the Miller Creek basin, the retirement of water rights
and commensurate agricultural acreage yields a much smaller improvement
in streamflow than first predicted.
The proposed mitigation is now in doubt because the Port’s original
assumptions about whether and how much water was being used by riparian
property owners have turned out to be false.
Notwithstanding this empirical information, the Port, without
justification, continues to utilize its original discredited assumptions
for those parcels where the Port’s consultant was unable to obtain actual
usage data. These assumptions
are not defensible where the Port’s own research has shown them to be
false. CSMP, Table G-2. Moreover, when empirical data is coupled with
hydrologic analysis, the results reveal an alarming trend. The Port’s Low Streamflow Analysis indicates
that the Port’s proposed Miller Creek water rights retirement will result
in a net decrease in streamflow, due primarily
to the dependence of a number of small farms on imported municipal water
as a source of irrigation. Low
Streamflow Analysis, pp. 9-10.
The assumptions that underlie the CSMP’s discussion of augmentation
in the Des Moines Creek basin are similarly flawed. There is no mention of the significant water
rights problems associated with the Tyee Golf Course well. See discussion Section B.2 below.
The Department of Ecology acknowledges (personal communications
with Pat Svoboda and Dan Swenson of Ecology) that there are significant
questions about the validity of this water right and there is certainly
no guarantee whatever that any portion of the Tyee water right will
be available for transfer to streamflow augmentation purposes.
Moreover, the asserted relative benefits, asserted
in the CSMP, of the Des Moines Creek augmentation proposal are not supported.
The report asserts that an addition of 0.8 cfs will be adequate
to maintain a recommended in streamflow of 1.0 cfs, given that late
summer flow typically drops to “about 0.3 to 0.5 cfs.”
CSMP, p.6-10 to 6-11. The report then provides a paragraph of
discussion regarding the benefits to stream temperature and dissolved
oxygen that will result from this level of augmentation.
However, no data is provided to support the bare assertions that
under the proposed augmentation regime, baseline stream temperatures
will improve to the level required to meet water quality standards.
(2) Low
Streamflow Analysis
Earth Tech’s Low Streamflow Analysis (LSA) identifies five
low-flow “factors” that will contribute to augmentation in the three
subject stream systems. LSA
at pp. 4-5. These involve stormwater recharge and infiltration
in the embankment fill, in biofiltration strips adjacent to runways,
and in stormwater detention facilities.
The LSA frankly acknowledges that the model used by the Port’s
consultants to ascertain streamflow impacts cannot assess the benefit
that the Port claims will result from these three mitigation factors.
LSA, pp. 4-5. The lack of certainty surrounding the benefit
of these factors cannot be converted into the reasonable assurance necessary
for Clean Water Act Section 401 certification.
The fourth factor identified in the LSA involves the
change in flows in Miller Creek resulting from farm buy-outs and retirement
of associated water rights. LSA,
pp. 9-10. The LSA acknowledges
that this strategy will result in a net reduction in flow in Miller
Creek. See discussion of CSMP, above.
The fifth augmentation strategy, identified for the first time
in the LSA, calls for “managed release of stormwater from reserved storage.”
LSA, p. 5. An abbreviated description of this mitigation
proposal is found at pages 15-20. While
the Port has assured the Department of Ecology that a detailed description
of this option will be provided for public review, in fact that description
is nowhere to be found in the materials available at the commencement
of the public comment period. See
12/08/00 Final Draft Meeting Notes, Sea-Tac Airport Third Runway
401 Permit Negotiations, at p. 5.
In contrast to the CSMP, the Low Streamflow Analysis makes
no mention of use of the Tyee Golf Course well as a source of augmentation
for Des Moines Creek low flows. Significantly,
of the five factors identified in this report, only the managed stormwater
release option is available in Des Moines Creek. LSA, p. 5.
(3) Supplemental
Biological Assessment
The Port’s Supplement to the Biological Assessment (SBA) describes
yet another configuration of potential augmentation strategies. The three mechanisms identified in this document
include: (1) release of stormwater,
(2) pumped water from the Tyee Golf Course well, and (3) retirement
of water rights and water withdrawals.
SBA, p. 12.
The SBA’s discussion of the first option, release of stormwater,
does not indicate whether this release would be “managed” and “active”
as described in the LSA, or whether it merely represents passive infiltration
typical of most stormwater reservoirs. If the latter, the benefit, if any, of these releases on streamflow
are immeasurable, as acknowledged by the Port.
Moreover, the SBA states that the approximate 9 acre feet of
water required by this strategy would be stored in a separate vault. Where that vault would be constructed and its
relationship to the subject streams is not identified in any of the
Port’s submittals. SBA, p. 12. The location, construction, and operation of
such a vault poses significant issues that may not be deferred if reasonable
assurance is to be provided under the Clean Water Act.
The lack of modeling and measurement associated with the stormwater
release and water right retirement strategies does not provide assurance
that water quality and quantity standards will be met. Further, the confusing, contradictory array
of information provided in these documents is inconsistent with the
clarity and clear scientific basis necessary for reasonable assurance
concerning the type and efficacy of streamflow augmentation. These problems
are compounded by significant legal questions surrounding the water
rights associated with the augmentation strategies, even were they clearly
-- and consistently -- described.
C.
Water Rights
As an initial matter, it should be noted that Miller and Des
Moines Creek are closed to new water right appropriations. WAC 173-509-040(1). These closures constitute official acknowledgement
that the streams are fully appropriated and in fact lack adequate flow.
Any water right activity undertaken by the Port must provide
absolute protection from further degradation and impairment.
Postema v. Ecology, 11 P.3d 726 (2000).
(1)
Tyee Golf Course well
Pursuant to the CSMP and the SBA, the Port continues to propose
that it will pump water from the Tyee Golf Course well as a direct source
of water to augment streamflow in Des Moines Creek. This reliance is misplaced, because the water right at issue is
of dubious validity. Previous
correspondence to the Department of Ecology has described in detail
the problems with this water right.
See Attachment 1 (letter to Pat Svoboda dated 8/9/00). Clearly, Ecology may not rely upon the proposed use of this water
as a component of its reasonable assurance finding.
While the Department of Ecology is not currently even processing
a Tyee Golf Course water right change application, the Port apparently
believes that it will receive expedited processing pursuant to WAC Chapter
173-152. However, that rule
only allows expedited processing when an application will provide a
substantial enhancement to the natural environment or would provide
public water supply to meet general public needs.
WAC 173-152-050(3).
Neither factor applies here. The purpose of the airport project is “to meet the public need for
an efficient regional air transportation facility to meet anticipated
future demand.” Army Corps of
Engineers, Public Notice of Application for Permit, Reference No. 1996-4-02325,
p. 4. There is no “benefit”
to the natural environment that accrues from the project. The Port’s offering of “mitigation” for its environmental harm does
not convert a project which proposes to fill wetlands with 20 million
cubic yards of fill into one in which the natural environment is substantially
enhanced. Further, neither public
water supply nor public health or safety are benefited.
For
purposes of the Section 401 certification decision, the serious questions
surrounding ownership and validity of the Highline water “right” go
to the heart of the “reasonable assurance” standard.
Questions concerning this water transfer will not be resolved
in the time frame required for the Section 401 decision and indeed may
take years to resolve, especially if appeals are invoked.
The Department may not rely upon a speculative, unapproved transfer
application as a basis for certifying that adequate base flow will be
maintained in Des Moines Creek.
(2)
Miller Creek Water Rights Retirement
The Port proposes
to retire 18 acquired water rights certificates and claims on Miller
Creek, in order to mitigate base flow reductions in the Creek. LSA, p. 9.
These water rights are described in the Port’s Comprehensive
Stormwater Management Plan, Appendix G, Table G-2 (revised December
2000).
However, even according to the Port’s own analysis, the strategy
of purchasing and retiring water rights in the Miller Creek basin will
result in a net reduction in water flow. LSA, pp. 9-10. This result
is based on empirical analysis, which revealed that most of the riparian
landowners were not pumping water from Miller Creek, but were utilizing
imported municipal water for irrigation purposes.
Return flows of imported water added to flow in Miller Creek,
a phenomenon no longer at work since these parcels have been purchased
and vacated.
Further, while
the Port indicates intent to retire these rights to the Department of
Ecology, such an action does not of itself protect the water from future
appropriation. If the Port
intends to permanently dedicate this water to instream flow uses, it
must submit change applications to the Department that will ensure perpetual
protection for these rights. Otherwise,
even assuming some benefit from the relinquishments, the rights will
be available to others. Because many of these rights have been relinquished
for non-use, legally, such permanent dedication may not be possible.
See CSMP, Table G-2.
Nor is the
Port entitled to mitigation credit for what appears to be illegal commercial
irrigation on the Scarsella and Genzales properties. It is disingenuous for the Port to assert that “although the properties
do not appear to have a recorded water right or claim in Ecology’s files,
it is assumed that the farmer either has a permit that is not filed
with Ecology, or feels that they have a valid vested right for water.” See LSA, p. 10.
Neither “feelings”
nor unfilled “documents” alone guarantee a water right. The water code clearly requires either a permit
or a claim form be on file with the Department to establish all but
exempt ground water uses. RCW
90.03.010; RCW 90.14.041. In
their absence, it may be assumed that these water diversions are illegal. As such, they are not transferable and the
Port may not rely upon them as a basis for designing a permanent flow
augmentation plan.
In sum, the
Port claims that cessation of surface diversions will result in “a direct
and immediate benefit” to Miller Creek, but has placed information on
the application record about this strategy that proves the opposite
conclusion. The Miller Creek
“water rights cessation” analysis provides no basis for a finding that
water quality impacts associated with decreased base flows will be offset
under this strategy.
Further, from a legal perspective, the Port is not entitled
to credit for water rights that are not placed into trust water rights
status, pursuant to RCW 90.42 and protected as instream water rights. It is doubtful that most of these rights can
be placed into trust status. Therefore,
no legal benefit should accrue to the Port for retirement of these rights
and claims.
The Miller Creek water right retirement strategy provides no
assurance whatever that base flows and attendant water quality standards
will be met. A Section 401 certification
cannot issue based on the Port’s analysis of impacts to Miller Creek.
(3)
Stormwater Release
The Port’s submittals fail to identify exactly how the Port
proposes to augment low streamflow from stormwater releases. There appear to be two options: passive infiltration (SBA, p. 12), and active/managed
release (LSA, p. 5).
A passive system of release does not provide the assurance
necessary to certify that water quality standards will be met. It is axiomatic that, under a passive release
system, the Port cannot control when water will be available to augment
base flow. Hence, there is no
assurance that water will be available in the stream when it is needed. This problem is fully acknowledged in the Port’s
submittals, where it is stated that the Port is unable to model, measure
or predict when or how much water will travel through embankment fill
and other substrate to reach Miller, Walker and Des Moines Creeks. Clearly, there is no reasonable assurance here.
An active system of capture and release for streamflow augmentation
raises other problems. If the
Port wishes to engage in active/managed release of water to augment
flow, it must obtain a water right.
All waters of the state, including detained stormwater, belong
to the public. RCW 90.03.010. Any entity who intends to put water to use for a beneficial use
must obtain a permit. RCW 90.03.250.
“Beneficial purpose” is defined under the water code to include
“fish and wildlife maintenance and enhancement … and preservation of
environmental and aesthetic values.” RCW 90.54.020. As a corollary, unless the Port obtains a water right protecting
its augmentation water from appropriation by others, there is no reasonable
assurance that streamflow in the three stream systems will be augmented
in perpetuity, at the level necessary to maintain water quality standards.
Finally, both passive and active release raise questions about
the quality of water that is returned to the stream. Absent treatment, stormwater will likely contain
toxic pollutants from runways and other impervious surfaces, degraded
dissolved oxygen, sediment, and other water quality degradation. See, e.g., previous and February 2001
comments by Northwest Hydraulic Consultants.
Because the Port does not discuss where or how stormwater will
be released to the three stream systems, information about treatment
to meet water quality standards is entirely absent.
CONCLUSION
The Port has
offered a sketchy and conflicting array of streamflow augmentation concepts
in support of its proposal to expand the airport.
It is a fact that the proposed expansion, if approved, would
permanently eliminate and degrade important aquatic resources. Thus, the plans offered as mitigation must provide permanent, effective
solutions to prevent the loss of aquatic functions.
The Port’s
mitigation plans hinge upon the provision of water from an external
source. Yet none of the Port’s
various plans, discussed in this letter, identifies with any degree
of certitude a viable source of external water for augmentation.
When it comes
to water supply, reliance on assumptions is simply not an acceptable
approach. The Section 401 process
requires, above all else, assurance that the Port’s mitigation proposals
will adequately compensate for water quality degradation.
It is critical to have committed in legally reliable form the
sources of clean, cold water that will serve, in perpetuity, the project’s
mitigation requirements.
Given the water
supply problems associated with the Port’s previous Section 401 applications,
the omissions described herein are extraordinary. The Port has been aware for more than two years
that water supply is a significant issue that must be resolved in order
to present a complete and credible Section 401 application. Yet the Port has failed to step up to this
issue. The Department of Ecology,
on this basis, must deny the Port of Seattle’s Section 401 application.
Battle Mountain Gold proposed engineering and mitigation solutions
for its gold mine project which are reminiscent of the Port’s proposals
here. The PCHB, in reversing
Ecology's 401 certification of the Battle Mountain Gold project, made
some relevant observations about legal requirements for mitigation:
"The proposed mitigation . .
. is not legally sufficient
to meet the criteria for approval of the water right applications or
providing reasonable assurance for the § 401 Certification.
The physical knowledge of the affected lands is limited in critical
areas necessary to conclude that proposed mitigation water is sufficient
or that the water will be delivered in a timely manner to affected streams. The mitigation is therefore highly speculative
and uncertain. The same must
be said for the permanent engineered solutions offered for the shift
in a hydraulic divide. The proposal
in essence calls for re-plumbing a watershed with facilities that must
be maintained forever."
The PCHB concluded:
"The focus of our environmental
laws must be on preventing pollution and habitat degradation.
It is not legally sufficient to proceed with the proposed mine
without much more specific knowledge of the potential impacts from the
development and meaningful means of preventing and protecting against
the adverse consequences of the development.
The long-term engineered solutions proposed in this case are
legally insufficient."
Like BMG, the Port of Seattle is relying on models that cannot
fully assess the impacts to small streams. The Port proposes to "re-plumb" the Miller, Walker and
Des Moines Creek basins, and rely upon permanent engineered solutions
(water storage vaults, reservoir infiltration) that have not been developed
to a verifiable level and cannot be reliably said to work. The Port's proposal does not provide the reasonable assurance that
the 401 permit process requires.
Yours Very Truly,
Rachael Paschal Osborn Consulting Counsel to Airport Communities Coalition
|