|
Document reformatted for the the world wide web
16 February 2001
U.S. Army Corps of
Engineers ATTN: Jonathan Freedman, Project Manager
Washington State
Department of Ecology ATTN: Ann
Kenny, Environmental Specialist
Subject: Comments on Seattle Tacoma International
Airport Project Applicant: Port of Seattle Reference: 1996-4-02325 GeoSyntec Consultants (GeoSyntec) has
been retained on behalf of the Airport Communities Coalition to provide
a technical review of investigation, analysis and design relating to
construction of the embankment fill and West Mechanically Stabilized
Earth (MSE) Wall elements of the proposed Third Runway Expansion Project
at the Seattle Tacoma International Airport.
This letter summarizes GeoSyntec’s comments on these items.
Additional comments are included in this letter regarding the
proposed expansion of the Industrial Wastewater System Lagoon #3. Our technical review included the documents
listed in Attachment A to this letter.
·
there is insufficient laboratory
strength data for proper characterization of foundation soils, and the
limited data is being interpreted incorrectly, and in an unconservative
manner;
·
the extent of the potentially
liquefiable material may have been underestimated, and strength values
being assigned to liquefied materials are unconservative;
·
seismic stability analyses
are being performed incorrectly;
·
seismic design criteria
have not been well established, and thus it is impossible to determine
how the wall is intended to perform during an earthquake; and
·
the FLAC analysis being
performed to assess seismic performance of the wall has not been calibrated
or validated with any real data, and thus it is not possible to interpret
the results it provides.
The net result of these deficiencies is that the project proponent
has yet to demonstrate either that a stable wall can be economically
constructed or that the wall, if constructed, can withstand the seismic
loads to which it may be subjected without large, unacceptable deformations. Comment 1: The
West MSE Wall should be considered at least 153 ft high.
Comment 2: There is insufficient
laboratory testing data in the vicinity of the West MSE Wall relative
to the scale of the project.
Comment
3:
Laboratory strength test data is being interpreted in a manner
resulting in higher strengths than would typically be used in engineering
practice.
Comment 4: Potentially unconservative
strength values are being used in stability analysis.
Comment
5: Flaws in the liquefaction analysis of foundation
soils render the conclusion that the wall will not fail due to liquefaction
invalid. Because of these flaws,
the extent of potential liquefaction of the subgrade beneath the West
MSE Wall and the rest of the Third Runway project may have been underestimated.
Furthermore, Hart Crowser appears to have incorrectly applied
the screening criteria used to identify nonliquefiable soils.
These criteria are intended to identify material that is potentially
liquefiable. Inverting them
to identify soils that are not liquefiable is not appropriate. Hart Crowser states, “if any one of these criteria was not met,
the soil was deemed nonliquefiable.” [underlining added for emphasis]
The four screening criteria are: 1. (Fraction of fines finer than 0.005 mm – 5%)
< 15%; 2. (Liquid limit + 1%) < 35%; 3. (Natural water content + 2%) > 0.9 LL; and 4. Liquidity index ≤ 0.75.
Comment
6: Inappropriate selection of residual shear
strength values means that the conclusion that the wall will not slide
on its foundation in the aftermath of a major earthquake is not valid. The selection of residual strength values to
represent conditions after a seismic event is unconservative and some
values are based upon extrapolation beyond the range of past experience.
Comment
7: The methodology used in performing pseudo-static
(seismic) stability analysis is incorrect and may seriously underestimate the ability of
the wall to withstand seismic loads.
According to Hart Crowser, “We typically apply the seismic coefficient
to the most critical failure surface identified in the steady-state
condition.” No justification is given for using this methodology,
and it is in fact incorrect as the critical static (steady-state) and
seismic failure surfaces are frequently very different. Under pseudo-static conditions, a horizontal
acceleration is applied to the entire failure mass, which acts as a
destabilizing force. The computed
critical failure surfaces for the seismic case tend to be longer, extending
further back into the slope in order to collect more driving mass. The critical surface for the seismic case will
also frequently extend along a weak material interface, such as the
existing peat layer, or through the liquefied sand deposit.
Comment 8: There are inconsistencies
in the results of the Probabilistic Seismic Hazard Analysis (PSHA) performed
by Hart Crowser that cast doubt on the validity of the analysis.
The primary inconsistency in the PSHA is with respect to the
magnitude of earthquake assigned to the various probability levels addressed
in the analysis. Unless these
inconsistencies are resolved, we cannot determine whether or not the
design earthquake has been properly characterized.
Comment 9: The single time history
used to analyze the seismic performance of the wall does not provide
an appropriate basis for the conclusion that the wall can withstand
the design earthquake.
Comment 10: Seismic design
ground motion criteria have not been established and there do not appear
to be any established seismic performance criteria for the wall.
Comment 11: To our knowledge,
the computer program FLAC used to evaluate the seismic performance of
the wall in the design earthquake has never been demonstrated to reliably
predict seismic deformations of earth structures. Therefore, the FLAC analyses do not provide an appropriate basis
from which to conclude that the wall can withstand the design earthquake. We have additional concerns about the method
of performing the analysis relating to seismic input, method of dealing
with liquefaction, and residual strengths that are not properly documented
in the material available for review.
Additional Concerns
Comment 13: The use of Hollow
Stem Auger drilling techniques for obtaining blow counts in sandy soils
below the water table is not appropriate and can lead to erroneous results,
particularly in loose soils (e.g. liquefiable sands).
Comment 14: Plans for construction of the West MSE Wall
should include instrumentation for monitoring potential deformations
and stresses.
Comment 15: Use of the HELP model for the estimation of groundwater and creek recharge after construction
of the runway embankment may result in underestimation of subdrain capacity,
leading to a potentially destabilizing buildup of water in the subdrain. Use of the HELP model is noted briefly
in the presentation to the Technical Review Board (Hart Crowser, November
16-17, 2000). The Hydrologic
Evaluation of Landfill Performance (HELP) model was designed to determine
leachate generation in municipal solid waste landfills.
It has been shown to perform poorly in predicting maximum infiltration
rates through soil covers for landfills (e.g., in predicting the performance
of evapotranspirative soil covers) and thus would not be expected to
provide satisfactory predictions of infiltration through a soil berm
and into a drainage system. Comment
16: The proposed Industrial Wastewater System (IWS) Lagoon #3 expansion
project may need further review by the Washington State Department of
Ecology Dam Safety Office. The IWS Lagoon
#3 expansion project has apparently been reviewed and approved by the
Department of Ecology’s Dam Safety Office.
However, only limited documentation exists of the extent of the
review. Among the documents
provided, only one relates to review of geotechnical engineering assumptions
and analyses. This document
is a two page handwritten “Geotech Review” dated May 30, 2000 with initials
JML. The review ends with the following statement: Will need to complete our independent analysis
in future. But, by inspection
the current design is suitably conservative.
Time constraints presently do not allow doing the full blown
analysis. Again, this will be
done! The project of actual
building the containment berm is scheduled in 2001.
The question remaining is whether this “full blown” analysis
was in fact performed prior to approval of the plans, or whether the
project was approved “by inspection” alone.
No additional documentation has been provided which might clarify
this matter.
Comment 17: The Port of Seattle
must assess the impact of the Third Runway and infrastructure construction
on the fate and transport of contaminants in the Airport Operations
and Maintenance Area. In
the vicinity of the Airport Operations and Maintenance Area, known contamination
exceeds MTCA cleanup levels. To
our knowledge, there has been no evaluation of the impact of installation
of underdrain systems and utility corridors for the Third Runway project
and infrastructure construction on the fate and transport of contaminated
groundwater from these existing airport operations. The general groundwater gradient leads from the vicinity of existing
contamination towards the new project area and the potentially impacted
creek and wetlands. Evaluation
must be performed to assess the impact of new construction activities
on the potential for adverse impacts on water resources including the
effects of existing contamination. In summary, based on our review of the
available documentation, there appear to be critical deficiencies in
both the field and laboratory investigations performed for this project,
as well as in the analysis assumptions and methodologies used. We are very concerned
that these deficiencies could lead to a design of the embankment and
walls that could ultimately result in significant damage or failure
of the wall, particularly under the influence of a strong seismic event
in the Seattle area. As such,
we request on behalf of the Airport Communities Coalition that, prior to
regulatory certification or approval of the proposed Third Runway Project,
the applicant be required to respond to the issues raised in this letter,
and that we be granted the opportunity to provide follow-up review and
comment on that response.
Sincerely,
Patrick C. Lucia, Ph.D.,P.E.,G.E. Edward Kavazanjian, Jr., Ph.D.,P.E.,G.E. Principal
Principal
Enclosures: List of Documents Reviewed Discussion of Factor of Safety vitae
cc: Peter Eglick, Helsell Fetterman LLP Kimberly Lockard, Airport Communities
Coalition
Attachment AList of Documents Reviewed
“Evaluation of Retaining Wall/Slope Alternatives to Reduce Impacts to Miller Creek – Embankment Station 174+00 to 186+00,” Prepared by HNTB, Hart Crowser, Inc., and Parametrix, (No Date).
“Industrial Wastewater Treatment Engineering Report,” Kennedy/Jenks Consultants, December 1995 (incomplete).
“Approach to Stability
Assessment,” Hart Crowser Memorandum, August 18, 1998. “Geotechnical Engineering
Report – 404 Permit Support – Third Runway Embankment – Sea-Tac International
Airport,” Prepared for HNTB Corporation and The Port of Seattle by Hart
Crowser, July 9, 1999. “Subsurface Conditions
Data Report – 404 Permit Support – Third Runway Embankment,” Prepared
for HNTB Corporation and The Port of Seattle by Hart Crowser, July 1999. “Subsurface Conditions
Data Report – Borrow Areas 1, 3, and 4 – Sea-Tac Airport Third Runway,”
Prepared for HTNB and the Port of Seattle by Hart Crowser, September
24, 1999. “Sea-Tac Airport Third
Runway – Probabilistic Seismic Hazard Analysis,” Hart Crowser Memorandum,
October 8, 1999. “Hydrogeologic Investigation
Report – Industrial Wastewater System – Lagoon #3 Upgrade – Seattle-Tacoma
International Airport,” for the Port of Seattle by Kennedy/Jenks Consultants,
February, 2000. “Seattle-Tacoma International
Airport – Industrial Wastewater System Lagoon #3 Expansion Project,”
Plan Set, Kennedy/Jenks Consultants, March 13, 2000. “Project Manual, Including
Specifications, for Industrial Wastewater system Lagoon #3 Expansion
Project,” Port of Seattle, March 16, 2000. “Seismic Basis of
Design – Third Runway Project,” Hart Crowser Memorandum, April 10, 2000. “Geotech Review” –
Two page handwritten commentary on ISW Lagoon #3 project geotechnical
engineering report by Zipper Zeman Associates, Inc. by Washington State Department of Ecology Dam Safety Section, Initials
“JML,” Date May 30, 2000. “Subsurface Conditions
Data Report – West MSE Wall – Third Runway Embankment – Sea-Tac International
Airport,” Prepared for Port of Seattle and HNTB by Hart Crowser, June
2000. “Preliminary Stability
and Settlement Analyses – Subgrade Improvements – MSE Wall Support –
Third Runway Project,” Prepared for HNTB by Hart Crowser, June 2000. “Geotechnical Input
to MSE Wall and Reinforced Slope Design – Third Runway Embankment,”
Hart Crowser Memorandum, August 21, 2000. “Use of Advanced Testing
Data – Sea-Tac Third Runway Project,” Hart Crowser Memorandum, August
28, 2000. “Port of Seattle –
Sea-Tac International Airport – Reinforced Earth Design Calculations,”
Reinforced Earth Company, September 1, 2000. “Subsurface Conditions
Data Report – Additional Field Explorations and Advanced Testing – Third
Runway Embankment – Sea-Tac International Airport,” Prepared for HNTB
by Hart Crowser, September 5, 2000. “Methods and Results
of Liquefaction Analyses – Third Runway Embankment – Sea-Tac, Washington,”
Hart Crowser Draft Memorandum, September 7, 2000. “Stability Review
of RECo 30% Design – Third Runway Embankment Project,” Hart Crowser
Memorandum, November 9, 2000. “Seattle-Tacoma International
Airport – The Journey Begins Here – The Third Runway,” Presentation
by Hart Crowser to the Technical Review Board, November 16-17, 2000. “Proposed MSE Wall
Subgrade Improvements – Seattle-Tacoma International Airport,” Hart
Crowser Memorandum, December 8, 2000. Attachment BDiscussion of Factor of Safety
A computer program is used to evaluate the factor of safety of a given wall or slope geometry. The factor of safety represents the ratio between the strength of the soils and the forces of gravity that act on the slope. If the strength of the soil in the slope just equals the forces acting on the slope then the calculated factor of safety in the computer program will be equal to 1.0. Accepted engineering practice requires that the factor of safety be at least 1.5 under static conditions, indicating that the strength of the soils are at least 50% greater than the forces acting on the slope. This additional 50% factor of safety is intended to account for the uncertainties in the interpretation of the field and laboratory data. When evaluating the factor of safety against liquefaction during a seismic event, or under short term conditions such as construction, a reduced factor of safety is sometimes allowed. In all cases, there needs to be a margin of safety sufficient to protect against potential events, known and unknown, that could compromise the safety of the slope and lead to failure.
The computer analyses calculate the
resisting strength of the soil and the destabilizing forces acting on
specified potential failure surfaces within the slope.
The ratio of the strength along the specified surface to the
forces on that surface is then calculated as the factor of safety. There are an infinite number of surfaces within
the slope for which the factor of safety can be calculated. The computer program will search within the
slope to find the surface with the minimum calculated factor of safety. If artificial constraints are put into the
analyses, such as preventing the computer for search for the critical
seismic surface, then the program will find the minimum factor of safety
only within the limits of the constrained analyses.
If the analyses are improperly constrained or the slope is incorrectly
modeled (e.g., with incorrect soil strengths) then the minimum factor
of safety of the slope cannot be accurately evaluated. |
||